What can be a result of a disagreement in contracting?

Study for the DAU Contracting Certification Exam. Prepare with multiple choice questions featuring hints and explanations. Boost your readiness and confidence for the exam!

A result of a disagreement in contracting is often a claim for compensation. When parties to a contract disagree on terms, performance, or obligations, one party may seek restitution or compensation for losses incurred due to the perceived breach or failure of the other party to meet their obligations. This claim is a formal request or assertion for payment, typically backed by evidence of damages or non-fulfillment of the contract terms.

In many cases, claims arise from specific disagreements over deliverables, timelines, quality of work, or other stipulated provisions. The resolution might involve negotiation, mediation, or legal action depending on the nature and context of the disagreement as well as the terms outlined within the contract.

While there may be other consequences like immediate contract cancellation or cancellation of future contracts, these are not direct outcomes of a disagreement; they are potential actions following a more severe breach or unresolved issues. Similarly, an automatic contract extension is not a typical result of a disagreement, as it usually requires mutual consent rather than a response to conflict.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy