Which risk is considered high in a Cost Reimbursement Contract?

Study for the DAU Contracting Certification Exam. Prepare with multiple choice questions featuring hints and explanations. Boost your readiness and confidence for the exam!

In a Cost Reimbursement Contract, the government assumes a significant amount of risk, particularly in terms of covering contractor costs. This means that the government agrees to reimburse the contractor for allowable costs incurred during the performance of the contract. Since the contractor is not bearing the full financial burden of project expenses upfront, the government can face the risk of higher-than-expected costs.

If project expenses exceed initial estimates due to factors like scope changes, unexpected challenges, or inefficiencies, the government must cover those additional costs. This inherent responsibility places the government in a position of high cost risk, as they may not have complete control over the spending and cannot predict with certainty the total financial commitment at the outset of the project.

Other types of risks, such as contractor cost risk, cash flow risk, or performance risk, do not carry the same weight in this context. Contractor cost risk is somewhat mitigated in a cost reimbursement setup since the contractor is compensated for their expenses. Cash flow risk typically pertains to the timing of funding and payments, while performance risk relates to the contractor's ability to deliver on project specifications—not necessarily tied to cost reimbursement dynamics. Therefore, in a cost reimbursement scenario, the government’s exposure to cost overruns distinctly highlights the significant cost risk involved

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy